Upper Chichester Township
Township Milling and Resurfacing to start Wednesday, September 25, 2024
Township Milling and Resurfacing to start Wednesday, September 25, 2024
The roads listed below in Upper Chichester Township have been scheduled for Milling and Resurfacing:
Wednesday, September 25, 2024 through Wednesday, October 2, 2024
Residents are reminded to please remove all vehicles from the street by 7:00 a.m. No work will be performed on the weekend.
Residents will be able to access their homes, but traffic may be restricted and street parking will be prohibited until the work is completed.
Please do not drive through barricades, as these are placed for the safety and protection of the workers.
Unless absolutely necessary, please do not drive or walk across freshly tarred or paved street. The oils and tar will stain cars, clothes, carpet, etc.
If we are not there on the above date, we will be there on the following day. Remember: Only a short-term inconvenience for a better road!
Thank you in advance for your cooperation.
Street Schedules in Phase 1 are listed Below:
Tuesday, September 24
- Chelsea Parkway
Wednesday, September 25 - Milling
- Cherry Tree Road
- Bender
- Willers
- Riviera
Thursday, September 26 - Milling
- Belvue
- Marylyn
- 9th Avenue
- Broomall
Friday, September 27 - Finish Milling and Start Paving
Same order as above
Monday, September 30- Paving
Tuesday, October 1 - Paving
Wednesday, October 2 - Paving